Sub-report 1 on the bridge collapse at Tretten on 15 August 2022

Road traffic report 2023/03

On the morning of 15th August 2022, Tretten Bridge in Norway collapsed and fell into the river of Gudbrandsdalslågen and onto the E6 highway, after having been in operation for approx. 10 years. The NSIA, together with an external expert group, has carried out technical investigations with respect to the collapse. Due to the fact that it is important for society and for the continued operation of existing timber bridges to clarify the technical reasons for the collapse, NSIA has chosen to present the results from this extensive work in subreport 1.

Sequence of events and rescue work

There was no local warning that the Tretten bridge was about to collapse before a lorry and a passenger car drove onto the bridge at 07:33 in the morning. It was only when the lorry traveling east was about halfway across the bridge that the bridge started to deform, which was observed by the driver of the passenger car behind the lorry. The driver of the passenger car evacuated the bridge, while the driver of the lorry was evacuated with the help of a helicopter. None of the persons involved were seriously injured in the incident. The fact that there were only two vehicles on the bridge when it collapsed and no cars under the bridge on the E6 highway was essential to the extent of the consequences not being more severe. The rescue work was also carried out in a satisfactory manner.

Main conclusion of technical investigations

A number of hypotheses for the cause of the collapse have been investigated by the external expert group based on external input and available background material, as well as their own investigations and various testing of elements from the collapsed bridge. The NSIA has followed up the professional group's work closely and continuously, and fully supports conclusions of the expert group.

From this work, the most likely cause of the collapse appears to be so-called “block shear failure”  in one of the timber diagonal members near the river foundation in the western part of the river. This conclusion is supported by post-calculations of the capacity in the current connections in relevant diagonals, by calculated collapse scenarios, by witness observations, as well as by assessments of visual material and bridge elements from after the collapse.

Block shear failure as a form of fracture, can theoretically be triggered by a momentary overload from traffic, or from a gradual weakening of the capacity due to repeated heavy loading from traffic possibly together with other secondary effects (so-called fatigue). Based on known information about heavy vehicle traffic on the bridge, and based on the sequence of events prior to the collapse, it is predominantly likely that the fracture location in question has been exposed to weakening over time.

Calculation of potential fracture-connection in the relevant area shows a clear overutilization of the capacity in relation to the current design rules for timber structures. However, this set of rules had not been made applicable to the project at the time for designing Tretten Bridge. The failure mechanism in question was thus not checked for at that time. The control calculation gives a utilization rate of approx. 200% in relation to failure, including built-in safety factors in the regulations. A utilization factor of this order of magnitude indicates that a breach can occur for the largest dimensioning lorries or a collection of several such. However, there is no indication that the bridge has been subjected to such a load directly prior to the collapse.

The load on the bridge when it collapsed was significantly lower than what it was designed for. It is therefore likely that critical parts of the bridge were degraded as a result of fatigue in the timber. A calculation of the fatigue capacity at the connection in question based on the assumed volume of heavy traffic confirms that this is a likely scenario.

After the collapse of Perkolo Bridge in 2016, Tretten Bridge was re-calculated according to the current rules with check against block shear failure by the Norwegian Public Roads Administration. The same overutilization as calculated by the external expert group were then found, and it was recommended that the bridge should be strengthened at these connections. Such a strengthening was never implemented. The NSIA is critical that the Norwegian Public Roads Administration did not follow this up sufficiently as no measures or restrictions were implemented.

The NSIA believes that the collapse of Tretten Bridge highlights the necessity of performing block shear failure controls in the design of timber structures. With this as a background, NSIA issues a safety recommendation on recalculation and control of existing timber bridges against block shear failure.

Further investigations

Sub-report 2 will focus on bridge management and follow-up of Tretten bridge throughout the bridge's life cycle, based on the main findings identified through the technical investigations.


Published 15.08.2023

Safety recommendation

Safety recommendation Road no. 2023/10T

Tretten bridge collapsed on 15 August 2022 after being in operation for about 10 years, most likely as a result of block shear failure in one of the wooden diagonal members near the river foundation in the western part of the river. It is predominantly likely that the fractured connection in question has been exposed to weakening over time (fatigue). The NSIA considers that the collapse of the Tretten bridge highlights the necessity of control for shear block failure in Eurocode 5 NS-EN 1995-1-1.

The Norwegian Safety Investigation Authority recommends the Norwegian Public Road Administration, as the road authority, to convey to owners of timber bridges a recommendation to calculate and check connections under tension in the fiber-direction for shear block failure in accordance with Eurocode 5 NS-EN 1995-1-1, and to implement appropriate measures if over-utilization is found.

Facts

Location Tretten bridge, Country road 254, Øyer, Innlandet
Occurrence date 15.08.2022
Accident type Other accident
Road class County road
County Innlandet
Police Disctrict Innlandet
Vehicle type Passenger car, Truck and trailer
Type of Transportation Freight transport, Private transport
Road region Innlandet
Accident category Ulykke m/ kjøretøy over 7500 kg

Reports - same county

Reports - same vehicle type